Home / Guides / Panels & service
PANELS & SERVICE

SDG&E panel upgrade: the steps from quote to power back on

Step-by-step guide to a main panel or service upgrade in SDG&E territory: load calculation, permit, SDG&E request, disconnect, inspection and timelines.

By CL Electric · Reviewed by Christian Correia Lopes, owner, CSLB C-10 #1123510 · Updated September 25, 2026 · 5 min read

Key takeaways

  • Most San Diego panel upgrades need a city or county electrical permit and coordination with SDG&E to disconnect and reconnect service.
  • If you're only replacing the panel at the same size, it is often a same-day swap with a scheduled disconnect, inspection and reconnect.
  • If you're increasing service size (for example 100A to 200A), SDG&E reviews the request and may need to upgrade its equipment first.
  • SDG&E's published target for main panel upgrades is 30 business days on average and 45 business days maximum.
  • A load calculation tells you whether you need a bigger service at all — load management can sometimes avoid it.
SDG&E panel upgrade: the steps from quote to power back on

Two kinds of panel upgrades

Panel replacement at the same size — swapping an old, damaged or recalled panel for a new one with the same amperage. These are usually completed in a day: your electrician schedules the disconnect with SDG&E, replaces the panel, passes the city inspection and SDG&E reconnects.

Service upgrade — increasing the capacity coming into your home, most commonly from 100A to 200A, to support EV chargers, heat pumps, batteries, induction cooking or an addition. SDG&E has to review these requests because its service wires, meter or transformer may need to change too.

Step by step

  1. Site visit and load calculation. We look at your existing panel, meter, service conductors and what you plan to add, and run a load calculation per the electrical code (NEC Article 220). This decides whether you need a bigger service or whether load management will do.
  2. Fixed quote and scope. Panel or meter-panel combination, any grounding and bonding corrections, circuits to move, and whether the service location changes.
  3. Permit. We pull the electrical permit with your city (San Diego, Chula Vista, Carlsbad, etc.) or the County for unincorporated areas.
  4. SDG&E request (service upgrades). The request is submitted through SDG&E's builder services process. SDG&E assigns a project manager, reviews the design and load, and lets you know about any fees or utility-side work.
  5. SDG&E preparation. SDG&E orders materials, surveys the site if needed and schedules crews for any utility-side changes.
  6. Installation day. SDG&E disconnects power, we install the new panel, and the city inspector signs off. Plan for the power to be off most of the day.
  7. Reconnect and energize. After the inspection release, SDG&E sets the meter and restores power. We label the new panel and walk you through it.

How long does it take?

SDG&E's energization timeline guide lists a target of 30 business days on average and 45 business days maximum for main panel upgrades, measured from when your request is complete. Same-size panel replacements that don't need utility engineering are often scheduled much faster. Permit turnaround varies by city.

What affects the cost

  • Service size and whether the meter/panel combination must be replaced
  • Moving the service location or trenching for underground service
  • Grounding, bonding and code corrections found on older homes
  • Any utility-side work SDG&E requires
  • Drywall or stucco patching around the panel

Tips to avoid delays

  • Decide on future loads now — EV charger, battery, heat pump, spa — so the service is sized once.
  • Keep the panel and meter area clear and accessible for SDG&E and the inspector.
  • Ask about load management first: sometimes a smart panel or charger load sharing avoids a service upgrade entirely.

Common questions

Yes. SDG&E has to disconnect and reconnect service, and for service size increases it reviews the request and may upgrade its own equipment. Your electrician coordinates this.

Usually most of one day: SDG&E disconnects in the morning, the panel is replaced, the inspector signs off, and SDG&E reconnects.

Yes. Panel replacements and service upgrades require an electrical permit and inspection from your city or the County.
Reviewed by
Christian Correia Lopes — owner of CL Electric and licensed California C-10 electrical contractor (CSLB #1123510). CL Electric is a Tesla Certified Installer, Loxone Certified Installer and Generac Aligned Contractor serving San Diego and Orange County. LinkedIn · Verify license at CSLB

Sources

The CL Electric Power Letter

One practical guide a month

Straight answers on panels, EV charging, batteries, generators and SDG&E rules — from licensed San Diego electricians. No spam, unsubscribe anytime.

Call Text Free Quote